|
The negotiations
between the Ethiopian Electric Power Corporation (EEPCo) and the
National Electricity Corporation of Sudan (NEC) concluded without
resolution after four days of discussions last week.
The Ethiopia
Sudan Power System Interconnection Project negotiations, held at the
Addis Abeba Hilton Hotel from September 19 to September 22, 2006,
had three agendas that were to be addressed.
The negotiations
plan was to dedicate the first day to the feasibility study done by
consultancy company, Hifab; the second day was to look at the
construction agreement and the third day was to negotiate a power
purchase agreement and to draft and approved the minutes from the
previous meetings, so as to reach an agreement; but neither an
agreement nor a discussion as such had taken place between
representatives of both countries.
“Some minor
discussions were held on the power purchase agreement, how much
energy Ethiopia can provide and what type of electric power Sudan
needs, but the negotiations concluded without enough talks being
held,” said Tesfaye Batu, representative for EEPCo.
Although it was
expected for experts from both countries to hold talks on the three
agendas, the meeting was adjourned without any information as to
when and where the discussions were to continue.
In order for
Ethiopia to receive a 29.3 million euro loan from the World Bank, so
as to export electric power to the Sudanese border, it needs to sign
the Construction and Power Purchase Agreement; the deadline given
for signing and submitting the agreement to the World Bank is
October 2008.
“We believe that
there is ample time for us to fulfil the negotiations,” Tesfaye told
Fortune.
Sudan, on the
other hand, needs 26.5 million euros for the project.
EEPCo intends to install a double
circuit electric power transmission line that will carry 230kv over
296km from Bahir Dar to the Sudanese border town of Shehedi.
According to
information from the Ethio-Sudanese Power System Interconnection
Project Office at EEPCo, a request for the Expression of Interest
was issued by the utility so as to contract a supervising
consultancy firm; 13 companies submitted their interest. Companies
that have been short-listed for the next selection level will be
announced next week.
Information from
the Project Office shows that Ethiopia intends to export 200mw of
power to Sudan from the already existent double circuit power line
in the Northern part of the country.
Although both
electric corporations have not decided on a date for their next
negotiations, sources said that the Sudanese negotiators would
rather not have it before the end of Ramadan.
“The fact the
meeting ended before addressing the controversial topic of the power
purchase agreement will make the following meeting an even tougher
one,” a professional from the sector said.
An expert in the
field stated if EEPCo fulfils the power export project with Sudan,
it will hugely exceed projects that were planned to be overseen by
the Nile Basin countries, giving EEPCo great results.
While
negotiations between Ethiopia and Sudan were still underway,
Ethiopia and Kenya negotiations were taking place simultaneously in
different halls of the same hotel.
These talks ended
with the signing of a memorandum of understanding, confirming the
supply of electric power to Kenya in the coming 15 months.
In the future,
EEPCo intends to build a hydroelectric power generation station that
will supply 600mw with a capacity of 400kv double circuit electric
power to be transmitted to the Kenyan capital, Nairobi.
|