|
A building
constructed for the National Archive and Library Agency (NALA) is
still standing idle four months after its construction ended.
Sources disclosed
that the reason the Agency has not moved in and opened up for work
is because the construction company that built the new building,
Grace Construction, was not willing to hand over the keys to the
edifice.
A senior
management staff from Grace Construction told Fortune that
company refused to hand over the keys because they request
additional payment from the original contract amount of 21.6 million
Br.
To many industry
observers, the conflict stems directly from the government’s new
policy regarding local construction.
An expert from
the field told Fortune that although the Ministry of
Infrastructure used to be the deciding party in regulating price
increases and price variations on construction projects, this
responsibility has now been deferred to the developer and the
consultant, with the contractor staying out of the proceedings.
On July 8, 2006,
when the Ministry of Infrastructure was restructured into the
Ministry of Works and Urban Development, it stopped its regulation
works that formerly monitored price variation and the Archives
building project finds itself in the middle of this new procedure.
After beginning
construction work four years ago, design changes were made to the
building, which resulted in extra building expenses, according to
the contractor and the project consultant.
Since the Agency
was not willing to make payments based on these additional expenses,
although the changes were made, the construction company refused the
hand over.
Semere Mengistu,
Director of the Contract Administration Department at the state
owned Construction Design Enterprise S.C. (CDESCo) told Fortune
that due to the design changes as well as the increase in building
material prices, the cost of the edifice increased by about 33pc
from the agreed upon amount.
“Although we had
informed the Agency of the price variation two years ago, they were
unwilling to make the payments,” he said.
However, Grace
Construction disputes the consultant’s figures and claims it is
actually 46pc, which amounts to over five million Birr.
Nevertheless,
sources close to the issue, said that when CDESCo was calculating
price adjustments, the Agency provided incorrect figures in its
request to the government. CDESCo and Grace asked the Agency to
change its request, but it refused stating that it could not
repeatedly ask the government for a higher budget.
The over
60-year-old Agency has been located in an old building on the
Ministry of Culture and Tourism compound on Sudan Street, near the
Ministry of Health; the new building lies on a 1,000sqm of land in
this same compound.
The Agency had
wanted to relocate its 192 employees, as well as books and written
records that have been collected and stored over the past 60 years,
to its new offices.
According to the
contract between the Agency and Grace Construction, the construction
was to take two years but it nonetheless took four. But since the
reasons for the delay were based on design changes, neither party
placed any complaints on the missed deadline.
Semere said that
the construction company finished the building four months ago and
had started temporary delivery of the building, but because of the
construction price concerns raised recently, it had to postpone the
handover. All works were concluded, on September 15.
“Since I was out
of the capital, I did not personally witness the conclusion,” Semere
said.
Atsede Zeleke, the Agency’s Finance and
Administration head told Fortune that the reason that they
had not moved into the new building was not because of the dispute,
but simply because final touches had to be addressed.
“We will discuss
the payment issue and execute it, once we are sure that all works
have been completed and the keys are handed over,” she said, adding
that she believed this would be done this past week, but so far it
has not.
Grace
Construction, which was established by Gebremichael Markos 13 years
ago, is one of the top 25 construction companies in the country.
Other construction stakeholders are afraid that the Archive building
complication will quickly spread throughout the industry with the
Ministry’s new policy.
“This type of
working system will cause disagreement in the future,” a
professional from the field stated, adding that this will result in
many more court cases due to the situation. Grace Construction has
decided that if it is not paid its owed amount, then it will be
taking the dispute to court to have it resolved.
|