|
The effort by the country’s utility
monopoly, the Ethiopian Electric Power
Corporation (EEPCo), to develop a source of
electric power from coal deposits at Yayu,
over 600Km west of Addis, in Oromia Regional
State, will be hazardous to the environment
if it is implemented as planned.
FICHTNER, a European consultant hired last
December, submitted the first draft of its
study on March 8, 2006, and said the Yayu
coal mine “is not environmentally friendly”.
EEPCo wants to develop this reserve to an
industrial level in order to generate 600mw
power, significantly upgrading the 750mw
power generation capacity it has now. The
management was hoping that this could
contribute to increasing its existing
coverage of electricity from 15pc to 50pc in
five years.
Yayu is just one of the multiple projects
the Corporation is undertaking to meet its
target. The reserve, which is believed to
contain 100 million tonnes, was first
discovered 10 years ago when the government
was interested in erecting a fertilizer
manufacturing plant.
A Chinese company, COMPLANT, conducted an
environmental impact assessment that
warranted the setting up of projects in the
area, known to be a dense forest part of the
country and where coffee grows wild. The
price of UREA at the time, which was less
than the cost per tonne estimated from the
plant, discouraged any effort by the
government to pursue its plan.
The project was terminated in 1997 and the
site transferred to EEPCo, which established
an office under the Yayu Coal Mine and Coal
Fired Thermal Power Plant Complex. It wanted
to review the impact assessment conducted by
the Chinese company and hired FICHTNER for
1.3 million Br.
The new consultant sent two of its experts
in January to the site, together with two of
the Corporation’s staff. They produced 17
volumes each with 35 pages. Five other
experts of FICHTNER reviewed these reports
before they were submitted to the management
of EEPCo.
Says the draft report: “After a careful
review of existing studies with respect to
the chosen technology and design and
baseline conditions, FICHTNER comes to the
conclusion that the Yayu coal mine is
currently not environmentally friendly.”
An official from the Environmental
Protection Unit Planning Department of EEPCo
confirmed that the draft study has made it
to their desk.
“We are going through it, so we are unable
to comment now,” said the official.
The review, however, claims that the impact
assessment conducted by the Chinese firm
overlooked several factors in the study,
including a health and safety assessment, a
socio-economic survey, investigation of the
fauna as well as an environmental audit
compliance. It also discovered that the
Chinese firm had failed to produce a land
use plan and had not indicated how the ash
from the burned coal could be removed.
Representatives for the Chinese firm were
not available for comment.
Now the price of UREA has shot up in the
world market, COMPLANT has been awarded a 12
million Br contract to start a fresh study
on how to resurrect the government’s plan to
set up a fertilizer manufacturing plant in
the same area. Its managers signed a
contract with officials of Coal Phosphate
Fertilizer Complex Project Office, which is
under the Ministry of Trade and Industry,
just last week.
FICHTNER’s new study is a major setback to
EEPCo’s plan to build a generator at a cost
of half a billion dollars. Its tender to
hire a consultant that would do engineering
and procurement was opened last October.
Three joint ventures had responded: the
Americans Kuljian together with Mariston &
Mariston, FICHTNER with International Mining
Consultants, and Lahmeier with the Dutch
Mining Technology (DMT).
Sources disclosed to Fortune that EEPCo has
awarded this contract to Lahmeier and DMT
and signed a contract on February 3, 2005.
Corporation officials deny the existence of
such agreement.
“It is utterly erroneous that they have
signed this agreement,” said an expert from
the federal Environmental Protection
Authority.
He argues no project should be implemented
in and around Yayu before the impact of
projects on its rich wilderness is fully
discovered.
FICHTNER is expected to send a university
professor and head of the project office for
the study to deliver their presentation to
the management of EEPCo and its staff
involved in the project. According to
sources, they are scheduled to stay in
Ethiopia from March 27 to 31, 2006. The
final report by FICHTNER is due on April 4.
|