|
In most of the graphic reports he had with him
during an exclusive interview with Fortune on
May 21, 2009, the two lines overlapped to the most
part; this means the water level in most of the dams
has reached the lowest level and is decreasing with
the passage of each day. But Miheret asserts that
his engineers in charge of each dam are making sure
that the waters do not decrease significantly.
During normal power generation seasons where the
dams have enough water to generate power at their
fullest capacity, the daily average reduction in the
level of water is about, on average, 10cm to 20cm at
each of the dams. However, the energy crisis has now
forced EEPCo to allow a decrease of only one to two
centimetres each day. That is only possible by
cutting down on the supply to consumers.
"We have to make sure that the amount of water in
our dams will enable us generate power till the next
rainy season," Miheret said.
But for some keen observers, the current power
crisis is mainly due to poor planning in the early
years of the introduction of the free market
economic policy, as well as the inappropriate
structure under which EEPCo has been for the past
more than 17 years.
When the incumbent introduced its economic policy
about 17 years ago, it was expected that the economy
would eventually grow and there would be more
industries that demand more power. Nevertheless,
this was not accompanied by the continuous
construction of hydropower generation plants as
intensively as it has started to do years after, a
critical observer with deep understanding of the
sector, told Fortune.
"Thus, the crisis has come about not because of the
natural imbalance in supply and demand; though the
imbalance contributes somewhat, it is insignificant.
The core reason is the long period amounting to
years between the construction of power generation
dams, especially before the launch of the current
mega ones," the observer said.
The problem, which is due to the lack of
preparedness for the expected growth in demand, is
further aggravated by the absence of a separate
ministry that is focused on the power issues; EEPCo
had first been aligned to other government agencies,
such as those responsible for the development of
other infrastructure facilities, and is now under
the mining sector, so the power sector has not been
given due emphasis, this observer argues.
Miheret suggests that there are discussions within
the government about the structural issue. He also
believes that the ongoing construction of hydropower
projects have been initiated as projected moves to
respond to the expected increase in demand.
"There has never been a time where such huge
projects were undertaken simultaneously," he said.
Yet again, had it not been for the natural causes,
EEPCo would have hardly been in the current crisis.
For instance, in early April when the energy
authorities announced the power cut schedule, the
two major sources of electric power, Gilgel Gibe I
and Melkawakena dams - which have the capacity to
generate 184Mw and 153Mw, respectively, had water
volumes that allowed them to generate and supply
power for a month and a month and a half,
respectively.
"The hydrology in the existing dams was not in our
favour as it was not in line with the meteorological
or hydrological forecast we had for this year,"
Miheret, told Fortune indicating that
Ethiopia's energy supply is highly rain dependent,
as is the nucleus of its economy - agriculture.
The volume of water the dams received from the Belg
rains this year (Ethiopia's second rainy season
which lasts from February through April or sometimes
May) is significantly lower than what EEPCo had
expected, according to the CEO.
On the contrary, unlike in previous years, the delay
in the completion of the major hydroelectric power
projects, which used to be among the central issues
whenever there was talk of the power crisis, now
seems to have reached a point where it is unlikely
to be an issue anymore.
The combined 780Mw power EEPCo is set to get from
Tekeze and Gilgel Gibe (GG) II Hydroelectric Power
Generation dams, which will almost double the
current generation capacity, is now three to five
months away. The construction of Tekeze, for
instance, was finalized last year. However, one
thing it has in common with the already operating
dams is that it also depends on the expected rain in
the coming Keremt (the main rainy season that runs
from June through September). It will be
commissioned this year provided that it collects
enough water in the coming rainy season.
Also, one thing the Gishe woreda and the GG II
project site have in common, though located in
different areas - north and south west of Addis
Abeba, respectively - is the difficult terrain in
both places.
The problem at GG II is related to the nature of the
project itself. It is designed to generate 420Mw of
power using the water that comes out of the dam for
GG I where it generates 184Mw power. GG II does not
need its own dam because there are plans to use the
already regulated water from GG I dam after it has
generated power at the latter. But the construction
work on this project has not been a smooth one.
The geo-physical nature of the place had been a
fierce challenge to the project contractor, the
Italian Salini Costratori, which was awarded the
contract in 2004, and to EEPCo's engineers in charge
of the project. The major problem had come when the
over 25.8Km tunnelling scheme struck problematic
geological conditions. The Tunnel Bowring Machine (TBM),
a major piece of equipment, was stuck in the tunnel
where unexpected sandy soil and water springs turned
the 7.1m (diameter) tunnel muddy, slowing the last
stretch of digging. After a long delay due to that,
the tunnelling continued under harsh conditions due
to the underground humidity and associated risks.
Nevertheless, by Friday, May 22, 2009, only about
200m remained for the tunnel to be completed;
Semegnew Bekele (Eng.), GG II Project manager,
describes the work left as something within a
distance visible to the naked eye.
It is under the hostile conditions of underground
operations that people have worked for about five
years; their work included constructing the
powerhouse; concrete lining of the bowered tunnel
and of the one kilometre long each two penstocks
(metal tunnels of 3.8 diameter each) that pour the
water from the concrete tunnel to the turbines
(generators) with more power and acceleration; as
well as the installation of electro-mechanical and
hydro-mechanical parts, which are key elements of
the power generation.
The concrete lining of 1.6m width pre-casts
(pre-fabricated concretes) are fixed on the walls of
the bowered tunnel. Four pre-cast elements of 1.6m
width that form a ring (a circle) when plastered
onto the wall, reduce the diameter of the tunnel
from 7.1m to 6.3m. Thus, the actual diameter of the
tunnel the water runs through is 6.3m. The water
from GG I dam generates more power at GG II because
of the elevation difference created due to the
design at the latter, according to Semegnew. The
100m net head power of the water at GG I that
generates 184Mw would have 470m net head power as it
runs through the 1,000m long two penstocks of GG II;
this would increase the turbine circulation allowing
the generation of 420Mw, according to the Project
Manager; the plant has four turbines.
"You can increase generation by making elevation
differences," he told Fortune.
Other works, including installation of transmission
lines, have been finalized; GG II has its own
substation ready to handle power transmission. It is
also connected with the substations at GG End and
Sebeta II, which Miheret said is the first
transmission lines of their kind in Ethiopia due to
the higher voltage. The latter are alternative
routes for the mega power generation plant to feed
into the national grid.
While being a big achievement for both energy
authorities and those involved in its construction,
GG II also means different things for the two; for
the former it is a visible hope, as is Tekeze,
that they consider would bring them a lasting
solution for the power crisis that put them in the
quandary for consecutive years now. But for the
engineers in the field it is beyond that; it is an
engineering icon.
"It is a masterpiece," Semegnew told Fortune
in a tone of pride over the finalization of the
project that he has been in charge of for years; he
called it a "big achievement."
Though left with the 200 plus metres work on the
tunnel to start power generation, strict adherence
to international industry standards would still make
GG II wait for months before it is commissioned. In
addition to cleaning the tunnels, which includes
uninstalling the ventilation, electronic, railway
trail, and removing machineries from throughout the
over 25Km tunnel, there still needs to be
international standard tests conducted - dry, wet
and commercial tests of the entire system - before
its commissioning. The cleaning and the first levels
of the tests (the latter take months) are currently
underway, according Semegnew.
Like any of the power generation facilities in
Ethiopia, GG II, however, would likely be dependent
on nature's supply of water.
"Hopefully, the time GG II is going to be
commissioned, at the end of July, is going to be a
good season. But even with the minimum water level
where Gibe I can't operate, there is a possibility
of opening the bottom out-let gate [of Gibe I] to
let water into Gibe II to generate power from the
latter," Miheret told Fortune.
Nevertheless, whether power generation projects like
GG II and Tekeze would come to the rescue of the
people who have to suffer blackouts until July, or
whether abundant rainfall recovers the water levels
of the operating dams in the coming two months is
yet to be seen. But, whether this happens or not,
the people of Gishe Woreda would be likely to get
electricity for the first time.
The Eastern Region of EEPCo has started work to
install one or two diesel generators in Rabel town
to light the woreda for 18 hours a day. This move
has come only following an appeal by the people of
the woreda to Prime Minister Meles Zenawi who spoke
to them in Mehal Meda, another woreda in North Shoa,
as part of his trip to some rural parts of the
Amhara Regional State about a month ago.
But, they would be able to get power from the
national grid only when the 32Km road construction
from Mekoy area of Oromia Special Zone in Amhara
Regional State to Abuye Meda of the Woreda is
completed. This road would enable their woreda to
get connected to the power substation in Kemise
area.
|